The task within the project did synch with the web version. They simply do not have a project assigned to them and show
#null
They do not synch to the web version which still shows 3 projects.
-
04/19/2013 17:46#1PRO
-
04/19/2013 21:56#2PRO
This is now fixed. But the delay in the synch-up is a bit confusing.
I am leaving this issue opened just to get some rational about why there is such a delay in synching the projects while the tasks did synch immediately. -
04/20/2013 06:02#5PRO
@vtourvie
In a free account, sync takes place once only within 24 hours, and there is no auto-sync any more. For example, if the last manual sync happens at 23:30 today, the next can be triggered only after 24 hours. In addition, login will load the data from the server, so it is also a sync.
And, here, you said, there is such a delay in syncing the projects while the tasks did sync immediately. Do you manually sync after adding the projects and the task? If convenient, could you please give us the related screenshot with "#null" showed?
Sorry for any inconvenience. -
04/25/2013 04:05#6PRO
Thanks for your answer.
Note that I am in a free account but still in my Pro trial period,
I am using the tool extensively to see if I want to make it my GTD system,
so far I like it, especially the fact that it tries to stick to the GTD principles.
I reproduced the scenario with screenshots (the black parts in the screenshots are my
changes to hide my personal information):
- I added a task in the android web app and added a new project while I created the task.
- I saved the new task and then synched in Android the task (which was in the <today> list,
so I clicked the <synch> button when viewing the <today> list)
- The task appeared in the web app, but with a #null project
(See screenshot 1-NullProject.png)
- When browsing the list of projet, the new project appears but not in the project tree (see
screenshot 2-NotInProjectTree.png, there are 7 projects in the tree but 8 in the main
window)
- Eventually (not sure what it took) the project tree is updated and the task shows the
proper project (See screenshot 3-ProjectTreeComplete.png, there are 8 projets in both main
window and tree, and 4-TaskFullySynched.png, the correct projet is now associated with the
task) -
04/25/2013 09:10#8PRO
@vtourvie We will look into it ASAP. Sorry for any inconvenience.
-
04/26/2013 01:44#9PRO
@vtourvie We've attempted to fix it and please have a try now.
We are so sorry for the inconvenience that caused to you. -
04/26/2013 21:08#10PRO
This does not seem to be fixed.
- I create a task named test2task with a project named test2project in my Android phone.
- I synch it, it appears in the web app on my PC but lacks any project associated to it
(See screen shot entitled "1-tasksWithoutProject.png")
- I view the project list, the new project exists but not in the tree
(See screen shot entitled "2-ProjectMissingInTheTree.png"}
- I view the details of the project test2project, the new task test2task is in it, when I click on it,
it still shows that no project is associated to it (no # value), same as in the screenshot "1-tasksWithoutProject.png". -
04/28/2013 02:12#11PRO
@vtourvie We will soon check it again. So sorry for it.
-
04/30/2013 02:39#12PRO
@vtourvie
After sync successfully completes, please refresh the webpage or click on the "Reload the tasks list" at the bottom of the left side menu to check if the project information will be showed or not.