@Ineu
Hi,
Sorry for missing your reply.
Are these tasks repeat tasks or normal scheduled tasks?
Is the time correct in the task editing page? Could you please give me a task title which has this problem by private comments? It will be good if you could send me a screenshot.
Best regards,
Doit.im Team
Incorrect rescheduling
Continuing http://help.doit.im/topics/4838#comment-5 which received no comments.
So, today is Friday and I again have my Saturday tasks scheduled for today. The problem is the very same as in the comment in the link above. I have tasks with repeat set to 'Weekly on Sunday, Saturday", they should appear in 'Today' only on Saturday, but they are in 'Today' already, though it's only Friday. It all started after your timezone fix: http://help.doit.im/topics/4838#comment-3
So, today is Friday and I again have my Saturday tasks scheduled for today. The problem is the very same as in the comment in the link above. I have tasks with repeat set to 'Weekly on Sunday, Saturday", they should appear in 'Today' only on Saturday, but they are in 'Today' already, though it's only Friday. It all started after your timezone fix: http://help.doit.im/topics/4838#comment-3
-
11/14/2014 07:15#1PRO
-
11/14/2014 10:03#3PRO
@Ineu
Hi,
We have fixed this issue. But sorry that the tasks which have been created could not be fixed automatically. The tasks for the day after tomorrow will be right.
Every time we will create the repeat tasks for today and tomorrow. We fix the bug today. So it will work the day after tomorrow.
Sorry for any inconvenience brought to you.
Best regards,
Doit.im Team -
11/14/2014 10:21#4PRO
@wendy_only
Great, thank you.