@Kassy,

Here is some more feedback on Android Beta 5.06. Any new beta version coming on this week?

1. When selecting the time of 12:00pm, it will show up as 00:00pm on the selection box.

2. When using the Goal focus view, I am not able to open up any projects in the Active project list to see the tasks within each project. However, If there are simple tasks on the goal view that are not associated to a project then I can open up the task. When I open up the Goal view, I would like to see the individual tasks, plus the project tasks grouped by projects with the ability to collapse and expand each project as needed.

3. When my reminder alerts go off, doit crashes from time to time. It does not happen all of the time though. I do still have the v4 DoIT app installed since the v5 beta version is not full featured yet.

4. When I edit an already created task that is say is scheduled for 2pm and alter the date to tomorrow, the time gets automatically changed to the hour in the future and does not retain the original time. I'd prefer it retain the original time and not automatically adjust to the next closest hour.

5. When I go into a project from the project view, Doit will indicate that there is an open task to complete, but will not show that open task when I expand the project. It shows all of the completed tasks of the project but not the task that is scheduled for tomorrow. FYI..if I change the start date to "Today" instead of tomorrow, the task becomes visible.